Configuring the Production Order Forecast Accuracy Engine via UI
The Production Order Forecast Accuracy engine is used to calculate the accuracy of forecast data and compare the forecast data against actual production data. Users can create many different Production Order Forecast Accuracy Configurations which the engine uses to generate production order forecast accuracy reports. When the engine is run, it runs for all valid configurations simultaneously. These configurations are visible in the Production Order Forecast Accuracy Configuration Report.
Complete the following steps to run the Production Order Forecast Accuracy Engine:
Log in to the ONE system as a Production Manager.
Click Menu/Favs > Production Order Forecast Accuracy > New Production Order Forecast Accuracy Config.
In the NEO UI, users can click on the Menus/Favs icon on the left sidebar and type in the name of the screen in the menu search bar. For more information, see "Using the Menu Search Bar."
The New Production Order Forecast Accuracy Config screen appears.
Enter values for fields described in the table below. Fields with an asterisk ( * ) are required.
Field Name
Description
* Enterprise Name
Select an enterprise name using the picker tool for which the forecast accuracy is run.
* Organization
Select an organization using the picker tool for which the forecast accuracy is run.
* Tier
Select a product tier from the dropdown menu.
Site
Select a site using the picker tool for which the forecast accuracy data is needed.
Actual Source
Select the source of actual data from the dropdown menu. The available options are Production Order or Work Order.
* Aggregation Horizon
Enter a horizon for data aggregation (e.g. 1 week, 7 days, 30 days).
* Aggregation Horizon UOM
Select a unit of measure for the Aggregation Horizon field.
* Time Period Out
Enter the time out period for forecast accuracy. Use this field to configure how far out in the future to consider forecasts (e.g. 1 week out, 2 weeks out).
* Time Period Out UOM
Select a unit of measure from the dropdown menu for the Time Period Out field.
Click Create.
A success message appears.